Seattle Monorail Project

Lea+Elliott assisted the Elevated Transportation Company (ETC, the predecessor to the Seattle Monorail Project (SMP), since its very inception. Initially, most of this work was familiarizing the original ETC Board with the various monorail technologies and operating systems, analyzing possible routes in Seattle for alignment alternatives, operations and rough order of magnitude costs.

When the ETC was reconstituted after the Initiative 53 vote, Lea+Elliott was part of the team selected by ETC to perform preliminary planning, engineering and environmental studies. Lea+Elliott’s role was again primarily technology and operations based. The firm assisted in defining and analyzing a number of possible initial systems alternatives. A technology assessment was performed that included the widest possible interpretation of monorail technology. As a result, Lea+Elliott led a tour of Japanese monorail systems and manufacturing facilities. Alignments were developed that would serve the major ridership areas and be technically feasible for all potential monorail technologies.

System equipment capital cost and O&M cost estimates were developed and the final monorail plan was developed that was ultimately approved by the voters to form the SMP. Lea+Elliott was officially selected as the prime Systems Engineering Consultant for the SMP in March 2003, following voter approval of the Seattle Popular Transit Plan in November 2002.

 Operational train simulations were performed on numerous alignments and variations such as single tracking over the West Seattle Bridge. Operating plans were developed to meet ridership estimates throughout the design day and for special events at the stadiums. Specifically, Lea+Elliott modeled all system elements and tested the validity of the station platform designs. Special emphasis was placed on the larger volume stations, including Weller/King, the transfer point between several transportation modes. This particular station is also designed to serve nearby sports complexes, thus placing huge demands on this station before and after planned sports activities. Lea+Elliott evaluated passenger flow both horizontally and vertically, and determined the optimum number of fare gates. Peak hour boarding at this station are expected to be significant multiple times a year when a baseball event ends during the commuter peak hour.  

The firm's scope of work included monorail system programming and planning; preliminary engineering; fare collection; simulation modeling; facilities interface work; system safety and security; systems cost estimating; collaborative preparation of the RFQ and RFP documents; implementation phase services; community involvement; and the provision of project management services.

Following negotiation of a contract with a system supplier, funding for the project was repealed by the local voters

<< Back



© 2008 Lea+Elliott, Inc.