
WMATA photo courtesy of
Larry Levine |
WMATA Metrorail
Extension to Washington Dulles International Airport
When Washington Dulles
International Airport was being designed in the 1950’s,
the Federal Aviation Administration (FAA) decided to
construct a highway from the airport to Interstate 66
and the Capital Beltway. In 1964, four years before the
Washington, D.C. metropolitan area’s public transit
authority was even created, the FAA wisely reserved the
median of the airport access highway for a future
transit line.
After over four decades of
planning, the construction of that transit line is
poised to begin soon and Lea+Elliott is a member of the
program management team that will be driving it toward
completion.
The 23-mile Metrorail extension represents a 22 percent
increase in the length of the current system. The new
extension will tie Washington Dulles International
Airport to the greater Washington, DC metropolitan area,
including nearby Tysons Corner - the largest employment
center in Virginia. Due to the project’s scale, it has
been broken into two phases. Phase 1, estimated at over
$2.5 billion, includes five stations and extends the
system 11.6 miles. Phase 2 will follow soon after Phase
1 and will take the line another 11.5 miles to Dulles
airport and beyond, into Loudoun County. The first phase
of the project will be designed and constructed by
Dulles Transit Partners under a design-build contract
through the authorization of the Virginia Public-Private
Transportation Act of 1995.
Engaged as a key member of the program management team,
Lea+Elliott is leading the systems engineering, planning
management and FTA readiness areas. The program
management team works on behalf of the owner,
Metropolitan Washington Airports Authority (the Airports
Authority), to ensure that the overall procurement,
design, construction, and commissioning adheres to the
agreed-upon budget, work scope and schedule. The team
also supports the Airports Authority in its
relationships with the public and stakeholder agencies,
such as the Virginia Department of Rail and Public
Transit (VDRPT), the Federal Transit Administration
(FTA), the Washington Metropolitan Area Transit
Authority (WMATA), and Fairfax County.
Systems management is being led by Lea+Elliott’s Philip
Castellana. He leads the team’s efforts relative to all
systems engineering and rapid transit vehicle
engineering issues. These responsibilities include:
design and installation of the train control, traction
power, communications, and track subsystems; systems
integration; system safety and security; system testing
and commissioning; and preparation for the start of the
operations and maintenance phase.
The new system will be turned over to WMATA when
construction and testing is complete and the extension
is ready to carry passengers. Philip’s team is also
working closely with WMATA as it prepares to purchase
railcars, fare collection equipment and maintenance
vehicles for the new line.
Planning management efforts are being led by
Lea+Elliott’s Larry Miller, P.E., including critical
support functions such as risk assessment and
mitigation, FTA readiness, agency coordination,
congestion management, permitting, right-of-way
acquisition, property management, environmental reviews,
and value engineering. Most recently, Miller’s team has
been working closely with the FTA in the development of
a risk register that identifies and then mitigates high
risk items related to the project schedule and budget.
Lea+Elliott’s Michele Jacobson, AICP has been leading
the area of FTA readiness, helping the Airports
Authority establish itself as a new FTA grant recipient.
The original project sponsor, VDRPT, is handing the
project off to the Airports Authority, making the
Airports Authority the recipient of a $900 million grant
from FTA to build one of the largest transit projects in
the United States. Her responsibilities include the
preparation of FTA applications for the project to
advance into final design and ultimately receive its
Full Funding Grant Agreement. Her team also reviews the
designs for stations and facilities and monitors land
use permit applications with a focus on the compliance
of the design with the final environmental impact
statement and Record of Decision.
Under the current schedule,
critical milestones include: the start of utility
relocations in September 2007, approval to enter final
design in late 2007, and starting full construction in
2008.
<<
Back |