|
 |
Singapore Changi
International
Airport People Mover System
Lea+Elliott was selected as
part of a multi-disciplinary Master Plan team to address
all aspects of the intra- and inter-terminal automated
people mover (APM) system necessary for the planning and
conceptual design of Terminal 3. The firm's
responsibilities included development of an effective
plan for the inter-terminal people mover system at
Terminal 3, as well as integration with existing
Terminals 1 and 2, and provisions for future expansions
and connection to a new Terminal 4 complex. The
alignment, operational strategy, phasing, schedule, and
estimated system costs were developed as a part of the
overall conceptual plan. Lea+Elliott was subsequently
selected by Civil Aviation Authority of Singapore (CAAS)
in a competitive process to be its PMS/APM consultant.
This work included a full
analysis of the PMS/APM requirements due to significant
changes in Terminal 3 configurations and uses. This
detailed planning phase included existing ridership for
several future airport use scenarios, developing and
analyzing alignment and station alternatives, simulating
train operations and estimating capital and O&M costs.
The proprietary Lea+Elliott LEGENDS© models were used
for these analyses. We also developed basic requirements
and designs for stations and maintenance facilities.
Lea+Elliott developed the
Tender Documents in conjunction with CAAS. Our primary
responsibilities were: the Special Provisions, Technical
Provisions (Performance Specifications), Operating and
Maintenance Provisions, Reference Drawings, review of
the Instructions to Tenderers Submittal Requests, and
the development of the Pricing Forms and Tender
evaluation procedures. Lea+Elliott also led the Tender
evaluation process. The Tender was closed in May 2001
and three Tenderers were evaluated. Our recommendations
were then forwarded to CAAS.
Subsequent to our Tender
evaluation, and in an effort to reduce the PMS project
costs, CAAS decided to alter the System configuration,
as well as fleet and operational requirements. This
necessitated a second Stage Tender process. CAAS did not
add monies or scope to our contract and therefore
modified the Tender documents, and then evaluated the
re-submitted Tender offers.
The Phase 3 - Construction
Monitoring - portion of our contract with the issuance
by CAAS of a Letter of Acceptance to the selected
supplier, Mitsubishi Consortium (Mitsubishi Corporation
and Mitsubishi Heavy Industries). Our primary
responsibilities for Phase 3 were to monitor the
implementation of the PMS project with regard to
submittal reviews, value analysis, contractor oversight,
on-site quality review, factory tests and inspections,
on-site testing, and system commissioning.
<< Back |